The maximum runtime is set per partition and can be viewed either on the system with sinfo
or here. There is no minimum walltime (we cannot stop your jobs from finishing, obviously), but a walltime of at least 1 hour is encouraged. A large amount of smaller, shorter jobs can cause problems with our accounting system. The occasional short job is fine, but if you submit larger amounts of jobs that finish (or crash) quickly, we might have to intervene and temporarily suspend your account. If you have lots of smaller workloads, please consider combining them into a single job that uses at least 1 hour.
Select the project account
Batch jobs are submitted by a user account to the compute system.
- For each job the user chooses one project that will be charged by the job. At the beginning of the lifetime of the User Account the default project is the Test Project.
- The user controls the project for a job using the option --account at submit time.
For the User Account the default project for computing time can be changed under the link User Data on the Portal NHR@ZIB.
Codeblock | ||
---|---|---|
| ||
To charge the account myaccount
add the following line to the job script.
#SBATCH --account=myaccount
|
After job script submission the batch system checks the project for account coverage and authorizes the job for scheduling. Otherwise the job is rejected, please notice the error message:
Codeblock | ||
---|---|---|
| ||
You can check the account of a job that is out of core hour.
> squeue
... myaccount ... AccountOutOfNPL ...
|
Interactive Jobs
See according Section in the Quick Start Guide.
...
The part in the parenthesis just uses ls
to output all .inp files, counts them with wc
and then subtracts 1, since bash arrays start counting at 0.
Select the project account
Batch jobs are submitted by a user account to the compute system.
- For each job the user chooses one project that will be charged by the job. At the beginning of the lifetime of the User Account the default project is the Test Project.
- The user controls the project for a job using the option --account at submit time.
For the User Account the default project for computing time can be changed under the link User Data on the Portal NHR@ZIB.
Codeblock | ||
---|---|---|
| ||
To charge the account myaccount
add the following line to the job script.
#SBATCH --account=myaccount
|
After job script submission the batch system checks the project for account coverage and authorizes the job for scheduling. Otherwise the job is rejected, please notice the error message:
...
title | Example: out of core hour |
---|
...
.
...